Clinton West Planning Process Documents

This project began in July 2011.

Over a 12-month period, community residents, township officials and Franklin County planners developed a land use plan for the portion of Clinton Township west of the Olentangy River.

Public Meetings

We held three public meetings to gather community input. Materials from each meeting are posted below.

Public Meeting 1: Oct. 4, 2011

Public Meeting 2: Jan. 17, 2012

Public Meeting 3: Apr. 3, 2012

Working Committee Meetings

In addition to large-scale public meetings, we worked with a committee composed of residents, business owners, developers and others. This committee helped review public input and gave us detailed feedback during the planning process.

We held three working committee meetings plus one orientation session. Materials distributed at each meeting are posted below.

Orientation Meeting: Aug. 29, 2011

Current Conditions and Community Vision: Sept. 20, 2011

Policy Recommendations and Design Alternatives: December 6, 2011

Draft Plan: March 13, 2012