At the Franklin County Department of Sanitary Engineering, we are committed to maintaining and improving the essential infrastructure that supports our communities. Through ongoing and future projects, we work to ensure reliable water and sewer services and enhance system efficiency. From water main replacements and pump station upgrades, each project reflects our dedication to public health and long-term sustainability. 

Explore our projects from the past, present, and future to learn how we are building a cleaner, healthier future for our communities - one project at a time.

Current & Recent Projects

North Hague Avenue

north hague project.jpg

Project Location: The unincorporated area of land in Franklin Township along N. Hague Avenue, Trabue Road, Britton Avenue, and Cherokee Street

Project Scope:  To install 7,065 linear feet (LF) of sanitary sewer gravity main, 84 wyes, and 32 manholes. Resurfacing of roadways in affected areas. 

Need for Project:

  • As part of its Water Quality Partnership program, the County has identified several existing neighborhoods in the County where residents currently rely on Home Sewage Treatment Systems (HSTS) for sewage treatment and disposal. The goal of the County is to provide centralized sanitary sewer service to these neighborhoods to eliminate reliance upon HSTS’s and eliminate unsanitary conditions. 
  • The N. Hague Avenue service area within Franklin Township is one such area identified as needing centralized sanitary sewer service.

Project Schedule:  

  • Construction of the project is scheduled to start March 31, 2025.
  • Project completion is anticipated to be late February 2026.

  Project Cost Estimate:

  •  Design – $414,366.75
  •   Construction Administration/Construction Inspection – $280,531.20
  • Construction – $5,362,175.70
  • TOTAL PROJECT COST – $6,057,073.65

Project Funding:

  •  Franklin County Department of Sanitary Engineering has secured funding for construction from Ohio Environment Protection Agency’s Water Pollution Control Loan Fund and from the Ohio Public Works Commission.
  •  Additionally, funding for the Financial Assistance Program was secured from Ohio Environment Protection Agency’s Water Pollution Control Loan Fund.

Financial Assistance Program: 

Due August 1, 2025

N. Hague Ave Sewer Assistance Application(PDF, 218KB)

N. Hague Ave Sewer Connection Process(PDF, 150KB)

N. Hague Ave Assistance FAQs(PDF, 155KB)

Inah-Gladys Sewer

Inah-Gladys Project Map for Handout_FINAL.jpg

Project Location:   The area of land in unincorporated Prairie Township on the east side of Inah Avenue and the west side of Gladys Road north of Owen Steet and south of West Broad Street. (see map on back ).

Project Scope:  To install 3,330 linear feet (LF) of new 8-in sanitary sewer gravity main, 590 LF of laterals, 13 manholes, and 29 lateral connections. Resurfacing of roadways in affected areas.

Need for Project:

  • Only section of the County’s Sanitary District No. 4 service area that does not have access to sanitary sewer.
  • Aging onsite treatment systems and improperly functioning aeration systems discharge raw sewage into storm sewers and waterways, impacting human health and water quality of surrounding creeks/streams/rivers and aquifers.

Project Schedule: 

  • Construction of the project is anticipated to take approximately 5 months.
  • Project completion estimated to be completely by the end of 2024

Project Cost Estimate:

  • Design – $103,784.98
  • Construction Administration/Construction Inspection – $117,890.52
  • Construction – $1,655,170.00
  • TOTAL PROJECT COST – $1,876,845.50

Project Funding:

  • Franklin County Department of Sanitary Engineering has secured funding for construction from Ohio Environment Protection Agency’s Water Pollution Control Loan Fund and from the Ohio Public Works Commission.
  • Additionally, funding for the Financial Assistance Program was secured from Ohio Environment Protection Agency’s Water Pollution Control Loan Fund.

Kanawha-Rosslyn Sewer

FCSE_KanawhaRosslyn_PublicMtg_1_Presentation_FINAL-12-12-23.jpeg

Project Location:   The unincorporated area of land in Sharon Township along Rosslyn Avenue, W. Kanawha Avenue, Westview Avenue, Olentangy Boulevard, and Riverside Drive.

Project Scope:  To install 4,900 linear feet (LF) of sanitary sewer main, 3,400 LF of sanitary sewer laterals, construction of a pump station, and repavement of the streets following construction.

Need for Project:

  • In July 1992 Franklin County Public Health identified 24 areas within Franklin County that were in need of public sanitary sewer service.

  •  Kanawha Rosslyn is one of these areas identified, and one of the last remaining unsewered areas.

Project Schedule:

  • Construction of the project was scheduled to start February 2024.
  • Project completion is anticipated to be mid 2025

Project Cost Estimate:

  • Construction Administration/Construction Inspection – $7,828,189

Project Funding:

  • Franklin County Department of Sanitary Engineering has secured funding for construction from Ohio Environment Protection Agency’s Water Pollution Control Loan Fund and from the Ohio Public Works Commission.
  • Additionally, funding for the Financial Assistance Program was secured from Ohio Environment Protection Agency’s Water Pollution Control Loan Fund.

South Grener Avenue Sewer

processed-9E9F0064-E8C7-4FDF-BA6D-ABBB80D4EE28.jpegProject Location:

Located in Prairie Township, along South Grener Avenue.

Need for Project:

As part of Franklin County Sanitary Engineering's Sewer Condition Assessment project it was found that the sanitary sewer line that ran along S. Grener is structurally deficient. The main was identified in 2015 to be in need of lining. When we went to line in 2020, the condition of the main had deteriorated to point where it could not be successfully lined. It was removed from that project and made its own project.

Project Scope:

Franklin County Board of Commissioners, on behalf of the Franklin County Department of Sanitary Engineering, is replacing approximately 812 LF of aging 15-in sanitary sewer and 40 LF of 8-in sanitary sewer with new 15-in and 8-in sanitary sewer, respectively, including all manholes, on South Grener Avenue near Stiles Drive in Prairie Township. Additionally, the project includes the transfer of approximately 12 existing sanitary sewer laterals to the proposed sewer. Roadway restoration will include full-width planing and resurfacing of approximately 1,925 SY of asphalt.

 

Past Projects 

Sewer Treatment and Collection System Projects

 Project Township  Tributaries  Year Completed 
Darbydale Wastewater Treatment Plant Pleasant 
  • Darbydale
  • Community Gardens Manufactured Home Community (MHC)
  • Pleasant Acres MHC
  • Oak Hills MHC
  • Timberlake Subdivision
  • Timberlake Water Treatment Plant
  • Village of Harrisburg

2019

(Constructed 2005)

 Holton Park Wastewater Treatment Plant Jackson
  • Holton Park
2015 
 Taylor Estates Wastewater Treatment Plant  Plain
  • Taylor Estates
2012 

Sanitary Sewer Improvements per Water Quality Projects

Project  Township  Connections  Year Completed   Cost Map 
 Mon-E-Bak Mifflin   360 2017  $4,129,106.36

 

 
Mon-E-Bak Tributary Map(PDF, 206KB)  
Brown Rd East   Franklin   290 2017  $2,431,885.17 Brown Road Tributary Map(PDF, 209KB)  
 Eureka Park Franklin  68  2015   $1,557,401.91 N/a 
Village of Harrisburg  Pleasant  164 2011   N/a N/a 
Fern Agler   Mifflin   25

2010

$137,666  N/a 
 Timberlake Subdivision  Pleasant   198 2010 N/a N/a
 Cleveland Heights Phase 3 Blendon   58 2010  $887,086.98  N/a
 Leonard Park Mifflin  166  2006  N/a  N/a 
 Harrisburg Pike Jackson   3 2005 N/a N/a
 Darbydale  Pleasant  774 2005  N/a  N/a 
 Brown Rd West  Franklin 55  2005  N/a  N/a 
 Briggsdale  Franklin 56   2005 N/a  N/a 
 Englewood Mifflin  19  2004  N/a  N/a
 Cleveland Heights Phase 1 & 2  Blendon  127  2004  N/a N/a 
 San Margherita  Franklin 164  2003 N/a N/a 
 Marsdale  Prairie  22 2000  N/a N/a 
 Emmit / Mix  Prairie  62 1998  N/a N/a

Pump Station and Force Main

 Project  Township Install Date
Oakhurst Knolls Pleasant 2020
Century Acres  Madison 2021
Young Estates Prairie 2021
 Mon-E-Bak and Brown Road East  Franklin 2016
Cherrydale Pump Replacement Madison 2016
Taylor Estates Plain 2012
Timberlake Pleasant 2012
 Villlage of Harrisburg Pleasant 2010 
Cherrydale Madison 2010
Village Park Prairie 1991
Timberbrook Norwich 1982

Water Treatment and Distribution System Projects

 

 Project Township Completion Date
Little Farms Water Distribution Improvements Prairie  TBD
Timberlake Elevated Tank Rehab Pleasant   TBD
Timberlake Water Treatment Plant Pleasant  2019
West Broad Street Waterline Replacement Prairie  2016
SD4 Water Distribution System Valve Replacement Prairie  2016
Leonard Park Water System Improvement  Mifflin 2016
Glenford Village Condominium Master Meter & Backflow Prevention System  Prairie  2015 
West Broad Street Waterline Replacement Prairie 2013 
Beacon Hill Road and Drainage Improvements Prairie  2013 
Woodlawn Avenue Road and Drainage Improvements Prairie  2013 
Timberlake Subdivision Water Treatment Plant Pleasant 2011
Village of Harrisburg Water Distribution System Pleasant 2010

Future Projects

Franklin County Sanitary Engineers in investing in key infrastructure upgrades to support our growing community and improve service reliability. Projects on the horizon include:                                                                        

  • S. Grener Avenue, Emmit Avenue, Mix Avenue, and Sullivant Avenue (GEMS) Water Main Replacement
  • Timberbrook Pump Station 
  • Village Park Pump Station
Stay tuned for updates as these projects move forward!